Donivy Lane Pavement

Project Description:

Reconstruction of 700 m existing road pavement and table drains, including construction of a new base layer and 2 coat bitumen seal. 

Scope:

  • Subgrade preparation
  • Clearing and grubbing
  • 2 coat bitumen seal
  • Pavement construction
  • Drainage infrastructure
  • Traffic control

Value Add:

Liaison with adjacent property owners affected by the works to ensure access requirements were satisfied at all times.