Project Description:
Construction of 15 x concrete floodways (30m x 8m) and 1 x major large cell RCBC crossing.
Scope:
Environmental management, traffic management, RCBC installation, concrete works, rock protection, pavement construction, 15 x concrete floodway construction.
Challenges:
Logistically challenging due to the 16 x different locations of each floodway site – thorough planning and communication were the key to the successfully delivery of each site.